TABLE OF CONTENTS

 

EXECUTIVE SUMMARY

Introduction

Environmental Monitoring Works

Environmental Licenses and Permits

Environmental Mitigation Implementation Schedule

Key Information in the Reporting Month

Summary of Complaints and Prosecutions

Future Key Issues:

1.     INTRODUCTION

Background

Project Organizations

Construction Programme

Summary of EM&A Requirements

2.     AIR QUALITY

Monitoring Requirements

Monitoring Locations

Monitoring Equipment

Monitoring Parameters, Frequency and Duration

Monitoring Methodology and QA/QC Procedure

Results and Observations

3.     NOISE

Monitoring Requirements

Monitoring Locations

Monitoring Equipment

Monitoring Parameters, Frequency and Duration

Monitoring Methodology and QA/QC Procedures

Results and Observations

4.     ENVIRONMENTAL AUDIT

Site Audits

Implementation Status of Environmental Mitigation Measures

Review of Environmental Monitoring Procedures

Status of Environmental Licensing and Permitting

Status of Waste Management

Implementation Status of Event Action Plans

Summary of Complaints and Prosecutions

5.     FUTURE KEY ISSUES

Key Issues for the Coming Month

Monitoring Schedule for the Next Month

Construction Program for the Next Month

6.     CONCLUSIONS AND RECOMMENDATIONS

Conclusions

Recommendations for next reporting month

 

 

LIST OF TABLES

 

Table I   Summary Table for Non-compliance Recorded in the Reporting Month

Table II  Summary Table for Key Information in the Reporting Month

Table 1.1  Key Project Contacts

Table 2.1  Locations for Air Quality Monitoring

Table 2.2  Impact Dust Monitoring Parameters, Frequency and Duration

Table 2.3  Summary of 1-hour and 24-hour TSP Monitoring Result in Reporting Month

Table 3.1  Locations for Noise Monitoring Stations

Table 3.2  Noise Monitoring Parameters, Frequency and Duration

Table 3.3 Summary the Noise Monitoring Results in Reporting Month

Table 4.1  Observations of Site Audit

Table 4.2  Summary of Environmental Licence / Permit for DE/2018/17

 

 

LIST OF FIGURES

 

Figure 1   General Location Plan of the Project and Locations of Air Quality and Noise Monitoring Stations

Figure 2   ET’s Organization Chart

 

 

LIST OF APPENDICES

 

A     Action and Limit Levels for Air Quality and Noise

B     Summary of Exceedance

C     Site Audit Summary

D     Summary of Amount of Waste Generated

E      Event Action Plans

F      Environmental Mitigation Implementation Schedule (EMIS)

G     Complaint Log

H     Construction Programme

 

 

ABBREVIATION AND ACRONYM

 

AL Levels               Action and Limit Levels

DSD                        Drainage Services Department

E / ER                     Engineer/Engineer’s Representative

EIA                         Environmental Impact Assessment

EM&A                    Environmental Monitoring and Audit

EMIS                      Environmental Mitigation Implementation Schedule

EP                           Environmental Permit

EPD                        Environmental Protection Department

ET                           Environmental Team

HVS                        High Volume Sampler

IEC                         Independent Environmental Checker

RE                           Resident Engineer

RH                          Relative Humidity

QA/QC                   Quality Assurance / Quality Control

SLM                        Sound Level Meter

WMP                       Waste Management Plan

SCISTW                 Stonecutters Island Sewage Treatment Works

HATS Stage 2A      Harbour Area Treatment Scheme Stage 2A

BSJV                       Bestwise - Sun Fook Kong Joint Venture